On January 21, 2022, the District Court for the Southern District of Georgia issued an Order in Georgia v. Biden, No. 2:21-cv-163 (S.D. Ga. Jan. 21, 2022), which responded, in part, to the Government’s requests for clarification regarding the scope of the court’s nationwide injunction of the federal contractor vaccine mandate promulgated under Executive

John Nakoneczny
GSA Will Insert FAR 52.223-99, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors in Multiple Award or Federal Supply Schedule Contracts for Products and Services
Following President Biden’s announcement of Executive Order 14042 (“EO”) on September 9, 2021, several agencies have issued guidance on the EO’s applicability to the contractor community, which we reported on here. Further to GSA’s September 30, 2021 Class Deviation CD-2021-13, on October 6, 2021, GSA reiterated that a mass modification program for all…
Laches Defense No Longer Available in ASBCA Appeals
In Lockheed Martin Aeronautics Company, ASBCA No. 62209 (a C&M case), the Board granted Lockheed Martin’s motion for summary judgment on the issue of whether the Government can assert laches as an affirmative defense to a Contract Disputes Act claim. In a case of first impression, Lockheed Martin argued that the affirmative defense of…
Federal Circuit Affirms Board Decision on Pandemic-Related Claim
The Federal Circuit recently affirmed the Civilian Board of Contract Appeals’ (CBCA) decision denying a pandemic-related claim in Pernix Serka Joint Venture v. Secretary of State, CBCA No. 5683, 20-1 BCA ¶ 37,589. Pernix involved a firm-fixed-price construction contract in Sierra Leone that was impacted by an Ebola outbreak several months into the project. The Department of State (DOS) declined to provide direction or to issue a suspension of work order, and instead advised Pernix to make its own business decisions regarding performance and employee safety. Pernix chose to demobilize its workforce and, later, to remobilize with the addition of its own on-site medical facility and services. Pernix then submitted a claim for the increased medical, safety, and demobilization and remobilization costs. DOS granted an adjustment to the schedule for the Ebola-related delays under the contract’s excusable delay clause, but denied Pernix’s monetary claim.
Continue Reading Federal Circuit Affirms Board Decision on Pandemic-Related Claim
Time is Money: Contractor’s Claims for Payment Dismissed
In URS Federal Services, Inc., ASBCA No. 62475 (March 23, 2021), the Board dismissed a contractor’s three-count complaint for lack of jurisdiction on one count and for failure to state a claim on the other two. The Board first addressed Count III, which alleged that the Government had breached the implied duty of…
Not So Fast: An REA that Does Not Seek a Final Decision Is Not a CDA Claim
In BAE Systems Ordnance Systems, Inc., ASBCA No. 62416 (February 10, 2021), the Armed Services Board of Contract Appeals addressed whether an request for equitable adjustment (REA) constituted a Contract Disputes Act (CDA) claim. BAE submitted a series of REAs that it consistently labeled and characterized as such and certified in accordance with…
Show Me The Money (Or GFE): FAR 52.245-1 Required Contracting Officer to Consider Equitable Adjustment for Missing Equipment
In BGT Holdings, Inv. v. United States, No. 1:18-cv-00178-PEC (Fed. Cir. Dec. 23, 2020), the Federal Circuit held that FAR 52.245-1 requires the Government to consider an equitable adjustment when it fails to provide Government-furnished equipment (GFE) required by the contract. The contract in question required the Government to furnish equipment for the construction…
Section 3610 of the CARES Act Extended Until March 31, 2021
On Sunday, President Trump signed a combined COVID-Relief and Omnibus Spending Bill, The Consolidated Appropriations Act of 2021, which funds the Federal Government for FY 2021 and includes a variety of COVID-19-related relief measures. Among those measures, Section 1002 of the Act extends the reimbursement period for Section 3610 of the CARES Act, which…
DoD OIG Audit Assesses Implementation of Section 3610 Relief Under CARES Act
On December 9, 2020, the Department of Defense Office of Inspector General (DoD OIG) released its Audit of Department of Defense Implementation of Section 3610 of the Coronavirus Aid, Relief, and Economic Security Act. The audit assesses the DoD’s issuance of relief under Section 3610, which authorizes certain agencies to reimburse contractors for any…
Application of the Spearin Doctrine Entitles Contractor to Recover FCA Litigation Costs
In Tolliver Group, Inc v. U.S. (Jan. 22, 2020), the Court of Federal Claims granted summary judgment in favor of a contractor who sought reimbursement of legal fees incurred in successfully defending against a False Claims Act (FCA) suit filed by a relator. The qui tam action arose from a defect in the original contract—the…