The Armed Services Board of Contract Appeals (Board) recently issued notable reminders to contractors regarding its jurisdictional authority and the importance of timely filing claims. The Board explained in DSME Construction Co., Ltd., ASBCA 63878 (July 30, 2024), that it may retain jurisdiction over a dispute even when a different forum is listed in the contract. In Platinum Services., Inc., ASBCA No. 63878 (Aug. 1, 2024), the Board instructed contractors to be mindful of the CDA’s statute of limitations period, even when seeking to amicably resolve a dispute.Continue Reading Know Your Rights: SBCA Issues Two Important Reminders to Contractors
John Nakoneczny
John Nakoneczny is an associate in the Government Contracts Group in Crowell & Moring’s Washington, D.C. office.
John represents and counsels contractors from diverse industries on contract disputes and other government contract matters. Prior to joining Crowell & Moring, he clerked at the Civilian Board of Contract Appeals, where he supported its judges in resolving and mediating appeals under the Contract Disputes Act. John earned his J.D. from The George Washington University Law School, where he was the president of the Government Contracts Student Association and on the Federal Circuit Bar Journal. While in law school, John served as a legal intern at the U.S. General Services Administration and the Fraud Section of the U.S. Department of Justice, Criminal Division. Upon graduation, John was awarded the President’s Volunteer Service Award.
An Uplifting Tale: Crane Supplier Recovers Breach Damages Because Commercial-Item Contract Did Not Incorporate Stop-Work Clause
In Konecranes Nuclear Equip. Servs. LLC, ASBCA, Nos. 62797, 62827 (May 7, 2024), the Armed Services Board of Contract Appeals (Board) awarded approximately $4.9 million in delay-related breach damages to Konecranes Nuclear Equipment Services (Konecranes) due to the Navy’s breach of its implied duty to not interfere on a commercial-item contract for the provision of 25-ton general purpose portal cranes.Continue Reading An Uplifting Tale: Crane Supplier Recovers Breach Damages Because Commercial-Item Contract Did Not Incorporate Stop-Work Clause
Funny Money: Federal Circuit Gives Its Two Cents, Reverses Dismissal of Implied-In-Fact Contract Claim
In Portland Mint v. United States, Case No. 22-2154, the Court of Appeals for the Federal Circuit reinstated the Portland Mint’s claim that the government breached an implied-in-fact contract to pay the Portland Mint for coins tendered under the government’s Mutilated Coin Redemption Program. The Court’s decision is a reminder of the jurisdictional importance in pleading a contract as implied-in-fact rather than implied-in-law. Continue Reading Funny Money: Federal Circuit Gives Its Two Cents, Reverses Dismissal of Implied-In-Fact Contract Claim
Board Sustains Lockheed Martin’s $131 Million Cumulative Impact Claim
In Lockheed Martin Aeronautics Company, ASBCA No. 62209 (a C&M case), the Armed Services Board of Contract Appeals (Board) awarded $131,888,860 in damages plus applicable interest in connection with Lockheed Martin’s claim for the cumulative disruptive impacts it experienced in performing over and above work on the C-5 Reliability Enhancement and Re-Engining Program. The…
You Need to Calm Down: Board Swift-ly Denies Motion to Dismiss for Failure to Prosecute Filed Just Days After Party Misses Deadline
In MLU Services, Inc. v. Department of Homeland Security, CBCA No. 8002, the Civilian Board of Contract Appeals (Board) denied a Federal Emergency Management Agency (FEMA) motion to dismiss for failure to prosecute, which the agency filed just four days after MLU failed to timely submit one of its initial pleadings.
This case…
Just Trust Me on This: Allegation of Contract’s Existence Is Sufficient to Establish Jurisdiction Under Contract Disputes Act
The U.S. Court of Appeals for the Federal Circuit held in Avue Technologies Corp. v. Department of Health and Human Services that an appellant’s non-frivolous allegation of a contract with the government via an end-user license agreement (EULA) incorporated into another contractor’s Federal Supply Schedule (FSS) agreement was sufficient to establish jurisdiction under the Contract Disputes Act (CDA).Continue Reading Just Trust Me on This: Allegation of Contract’s Existence Is Sufficient to Establish Jurisdiction Under Contract Disputes Act
CBCA’s FY 2023 Report – Examining the Numbers
The Civilian Board of Contract Appeals (CBCA) recently published its Annual Report for FY 2023, providing statistics regarding the adjudication of appeals between contractors and civilian agencies such as the Department of State, the Department of Veterans Affairs, the General Services Administration, the Department of Transportation, the Department of Agriculture, the Department of the Interior…
Board “Evicts” Government Termination: Contractor Awarded Expected Lost Profits for Improper Lease Termination
n Flatland Realty, LLC, ASBCA No. 63409, the Armed Services Board of Contract Appeals (Board) granted an appeal seeking damages, plus interest, from an improper termination for default. In an uncommon result, the Board awarded lost profit expectancy damages because the government had improperly terminated the contract, which did not incorporate a termination for convenience clause.Continue Reading Board “Evicts” Government Termination: Contractor Awarded Expected Lost Profits for Improper Lease Termination
ASBCA’s FY 2023 Report – A Look at the Numbers
On November 1, 2023, the Armed Services Board of Contract Appeals (ASBCA) published its FY 2023 Report of Transactions and Proceedings, which provides statistics regarding the adjudication of appeals between contractors and the Army, Navy, Air Force, Corps of Engineers, Central Intelligence Agency, National Aeronautics and Space Administration, Defense Logistics Agency, Defense Contract Management…
COVID Costs Claim Succeeds: Contractor Entitled to Recover for Performance of Contract Despite Base Closure
In StructSure Projects, Inc., ASBCA No. 62927, the Armed Services Board of Contract Appeals (Board) granted an appeal seeking recovery for increased costs resulting from the COVID-19 pandemic. The underlying task order involved design and alteration services for existing medical facilities at Travis Air Force Base, and included a specific Contract Line Item Number (CLIN) for the provision of temporary phasing facilities that the Government could use while the construction work was ongoing. When the pandemic began in March 2020, StructSure and its subcontractors had to stop their on-site construction work for 44 days because the Government had limited base access for contractors deemed to be not mission-essential. StructSure later sought schedule and monetary relief, but the Government only granted schedule extensions under the Default clause.Continue Reading COVID Costs Claim Succeeds: Contractor Entitled to Recover for Performance of Contract Despite Base Closure