On April 26, the Federal Circuit issued a decision in Crawford v. United States (a C&M case), holding that a U.S. Army combat veteran is entitled to recover his attorneys’ fees arising from a dispute related to obtaining medical retirement benefits earned during his service. In the underlying dispute on remand to the Army Board
Claims
YOLO: CBCA Finds that a Contractor Cannot Revive Its Expired Appeal Rights by Resubmitting a Claim




On April 6, 2023, the Civilian Board of Contract Appeals (CBCA), in BES Design/Build, LLC, CBCA 7585, dismissed a contractor’s appeal for lack of jurisdiction, finding the appeal untimely, and underscoring that a contractor cannot reset the 90-day appeal window by resubmitting its original claim.
On February 24, 2021, BES Design/Build, LLC (BES) submitted…
COFC: Strictly Scrutinizing the Completeness of the Government’s Administrative Record



Last week, the Court of Federal Claims issued a decision highlighting – and further widening – the gap between the limited agency record typically available to protesters at the Government Accountability Office (“GAO”) and the much more fulsome record available at the Court. In Trace Systems Inc. v. U.S., the Court signaled its increasing willingness to scrutinize the adequacy of the record produced, rather than simply accept Government representations of completeness.
Trace Systems considered a challenge to the cancellation of a competitive procurement in favor of a sole-source award by the Defense Information Systems Agency (“DISA”). After the Government filed an administrative record containing nearly 23,000 pages of documents purportedly detailing the cancellation decision, the protester objected and sought the production of additional documents, claiming only six of the originally produced documents were relevant. The Court ordered DISA to complete the record, and the Government produced additional documents. DISA explained, however, that it was withholding other records that were “internal, predecisional, and deliberative agency documents.” The protester again objected and asked the Court to compel the Government to file all relevant documents. In response, the Government represented that, beyond the pre-decisional documents it had withheld, the record was now complete.…
Just the (Same) Facts, Ma’am: ASBCA has Jurisdiction to Hear Contractor’s Different Theories of Recovery Based on the Same Set of Operative Facts



In ECC Int’l, LLC, ASBCA No. 60167 (Jan. 25, 2022), the Armed Services Board of Contract Appeals (“Board”) held that it had jurisdiction to hear a contractor’s alternate theories of recovery that arose from the same operative facts and sought the same relief requested in its claim. The contractor initially filed a certified claim for…
Federal Circuit Vacates COFC Decision Entitling Contractor to Damages for Breach of Implied Warranty Because the Contractor Did Not Present the Claim to the CO





In Tolliver Group, Inc. v. United States, No. 2020-2341, 2021 WL 5872256 (Fed. Cir. Dec. 13, 2021), the Federal Circuit vacated and remanded the Court of Federal Claims’ (“COFC”) decision holding that the contractor was entitled to an equitable adjustment for damages caused by the Government’s breach of the implied warranty that satisfactory contract…
The ASBCA Rejects the Navy’s Attempt to Use a Default Termination as a Sword and Shield



n Ultra Electronic Ocean Systems, Inc., ASBCA No. 62804 (June 17, 2021), the Armed Services Board of Contract Appeals (the “Board”) held that a contracting officer’s letter terminating the contract for default “effective immediately” constituted a Contracting Officer’s Final Decision for the purpose of granting the Board jurisdiction over the contractor’s appeal.
In Ultra…
Laches Defense No Longer Available in ASBCA Appeals





In Lockheed Martin Aeronautics Company, ASBCA No. 62209 (a C&M case), the Board granted Lockheed Martin’s motion for summary judgment on the issue of whether the Government can assert laches as an affirmative defense to a Contract Disputes Act claim. In a case of first impression, Lockheed Martin argued that the affirmative defense of…
Federal Circuit Affirms Board Decision on Pandemic-Related Claim






The Federal Circuit recently affirmed the Civilian Board of Contract Appeals’ (CBCA) decision denying a pandemic-related claim in Pernix Serka Joint Venture v. Secretary of State, CBCA No. 5683, 20-1 BCA ¶ 37,589. Pernix involved a firm-fixed-price construction contract in Sierra Leone that was impacted by an Ebola outbreak several months into the project. The Department of State (DOS) declined to provide direction or to issue a suspension of work order, and instead advised Pernix to make its own business decisions regarding performance and employee safety. Pernix chose to demobilize its workforce and, later, to remobilize with the addition of its own on-site medical facility and services. Pernix then submitted a claim for the increased medical, safety, and demobilization and remobilization costs. DOS granted an adjustment to the schedule for the Ebola-related delays under the contract’s excusable delay clause, but denied Pernix’s monetary claim.
Continue Reading Federal Circuit Affirms Board Decision on Pandemic-Related Claim
All Things Protest: Evolving Developments in Awardee Standing


Crowell & Moring’s “All Things Protest” podcast keeps you up to date on major trends in bid protest litigation, key developments in high-profile cases, and best practices in state and federal procurement. In this episode, hosts Christian Curran and Olivia Lynch discuss a recent Court of Federal Claims decision with interesting implications for awardee standing.…
“Here before. Many times. And without resolution.” – Board’s Dismissal of Contractor’s Appeals as Moot Precludes Analysis of Costs Repeatedly Disallowed on the Same Grounds




In L3 Technologies, Inc., ASBCA Nos. 61811, et al. (Mar. 1, 2021), the Armed Services Board of Contract Appeals (Board) granted the Government’s motion to dismiss the appeal, over the contractor’s objection, following the Contracting Officer’s (CO) unequivocal withdrawal of its cost disallowance claims. The contractor argued that its case was not moot despite…