In ECC Int’l, LLC, ASBCA No. 60167 (Jan. 25, 2022), the Armed Services Board of Contract Appeals (“Board”) held that it had jurisdiction to hear a contractor’s alternate theories of recovery that arose from the same operative facts and sought the same relief requested in its claim. The contractor initially filed a certified claim for
Claims
Federal Circuit Vacates COFC Decision Entitling Contractor to Damages for Breach of Implied Warranty Because the Contractor Did Not Present the Claim to the CO





In Tolliver Group, Inc. v. United States, No. 2020-2341, 2021 WL 5872256 (Fed. Cir. Dec. 13, 2021), the Federal Circuit vacated and remanded the Court of Federal Claims’ (“COFC”) decision holding that the contractor was entitled to an equitable adjustment for damages caused by the Government’s breach of the implied warranty that satisfactory contract…
The ASBCA Rejects the Navy’s Attempt to Use a Default Termination as a Sword and Shield



n Ultra Electronic Ocean Systems, Inc., ASBCA No. 62804 (June 17, 2021), the Armed Services Board of Contract Appeals (the “Board”) held that a contracting officer’s letter terminating the contract for default “effective immediately” constituted a Contracting Officer’s Final Decision for the purpose of granting the Board jurisdiction over the contractor’s appeal.
In Ultra…
Laches Defense No Longer Available in ASBCA Appeals





In Lockheed Martin Aeronautics Company, ASBCA No. 62209 (a C&M case), the Board granted Lockheed Martin’s motion for summary judgment on the issue of whether the Government can assert laches as an affirmative defense to a Contract Disputes Act claim. In a case of first impression, Lockheed Martin argued that the affirmative defense of…
Federal Circuit Affirms Board Decision on Pandemic-Related Claim






The Federal Circuit recently affirmed the Civilian Board of Contract Appeals’ (CBCA) decision denying a pandemic-related claim in Pernix Serka Joint Venture v. Secretary of State, CBCA No. 5683, 20-1 BCA ¶ 37,589. Pernix involved a firm-fixed-price construction contract in Sierra Leone that was impacted by an Ebola outbreak several months into the project. The Department of State (DOS) declined to provide direction or to issue a suspension of work order, and instead advised Pernix to make its own business decisions regarding performance and employee safety. Pernix chose to demobilize its workforce and, later, to remobilize with the addition of its own on-site medical facility and services. Pernix then submitted a claim for the increased medical, safety, and demobilization and remobilization costs. DOS granted an adjustment to the schedule for the Ebola-related delays under the contract’s excusable delay clause, but denied Pernix’s monetary claim.
Continue Reading Federal Circuit Affirms Board Decision on Pandemic-Related Claim
All Things Protest: Evolving Developments in Awardee Standing


Crowell & Moring’s “All Things Protest” podcast keeps you up to date on major trends in bid protest litigation, key developments in high-profile cases, and best practices in state and federal procurement. In this episode, hosts Christian Curran and Olivia Lynch discuss a recent Court of Federal Claims decision with interesting implications for awardee standing.…
“Here before. Many times. And without resolution.” – Board’s Dismissal of Contractor’s Appeals as Moot Precludes Analysis of Costs Repeatedly Disallowed on the Same Grounds




In L3 Technologies, Inc., ASBCA Nos. 61811, et al. (Mar. 1, 2021), the Armed Services Board of Contract Appeals (Board) granted the Government’s motion to dismiss the appeal, over the contractor’s objection, following the Contracting Officer’s (CO) unequivocal withdrawal of its cost disallowance claims. The contractor argued that its case was not moot despite…
Show Me the Money? When a Sum Approximate Counts as a Sum Certain






In Creative Management Services, LLC, dba MC-2 v. U.S. (Feb. 26, 2021), the Federal Circuit affirmed a Court of Federal Claims decision dismissing a contractor’s appeal of the government’s Contract Disputes Act (CDA) claim as untimely, holding that the contractor appealed more than 12 months after receiving a contracting officer’s (CO) final decision. On appeal, the contractor alleged that the final decision was not a valid claim because it did not state a “sum certain” as required by the CDA, and this deficiency meant that the 12-month appeal period had not started to run.
The contractor was awarded a General Services Administration (GSA) task order to provide marketing and logistical support for an annual GSA conference, and was required to keep the revenue it collected for the conference in a trust account. When GSA canceled the conference in the fourth year and asked the contractor to return all remaining money in the trust account, the contractor refused and submitted a termination for convenience proposal to GSA. GSA subsequently issued two letters to the contractor demanding an accounting of the trust account and all money that remained in it. The CO then issued a final decision on the contractor’s termination proposal and on GSA’s claim to the remaining funds in the trust account, without providing a dollar amount. The contractor filed suit three years after the final decision was issued, challenging the government’s claim to the trust account funds.…
Continue Reading Show Me the Money? When a Sum Approximate Counts as a Sum Certain
All Things Protest: COFC Deems Small Business Ineligible for Failing to Recertify as Other than Small under FAR 52.219-8 While Proposal Was Pending Following an Acquisition



In this episode, hosts Rob Sneckenberg and Olivia Lynch are joined by colleague Amy O’Sullivan to discuss the Court of Federal Claims’ recent decision in HWI Gear, Inc., which held that the solicitation’s inclusion in full of the text of FAR 52.219-28 required a small business offeror to recertify its size status prior to award…
Stopped in its Tracks: The Government’s Failure to Track Software Use Constitutes Infringement Under 28 U.S.C. § 1498




In Bitmanagement Software GmbH v. United States, the Federal Circuit vacated and remanded a decision by the Court of Federal Claims (COFC) that found the Navy was not liable for copyright infringement even though it was undisputed that the Navy made 429,604 copies of Bitmanagement’s BS Contact Geo software when it only paid for…