Photo of Skye Mathieson

In L3 Technologies, Inc., ASBCA Nos. 61811, et al. (Mar. 1, 2021), the Armed Services Board of Contract Appeals (Board) granted the Government’s motion to dismiss the appeal, over the contractor’s objection, following the Contracting Officer’s (CO) unequivocal withdrawal of its cost disallowance claims. The contractor argued that its case was not moot despite

In Creative Management Services, LLC, dba MC-2 v. U.S. (Feb. 26, 2021), the Federal Circuit affirmed a Court of Federal Claims decision dismissing a contractor’s appeal of the government’s Contract Disputes Act (CDA) claim as untimely, holding that the contractor appealed more than 12 months after receiving a contracting officer’s (CO) final decision. On appeal, the contractor alleged that the final decision was not a valid claim because it did not state a “sum certain” as required by the CDA, and this deficiency meant that the 12-month appeal period had not started to run.

The contractor was awarded a General Services Administration (GSA) task order to provide marketing and logistical support for an annual GSA conference, and was required to keep the revenue it collected for the conference in a trust account. When GSA canceled the conference in the fourth year and asked the contractor to return all remaining money in the trust account, the contractor refused and submitted a termination for convenience proposal to GSA. GSA subsequently issued two letters to the contractor demanding an accounting of the trust account and all money that remained in it. The CO then issued a final decision on the contractor’s termination proposal and on GSA’s claim to the remaining funds in the trust account, without providing a dollar amount. The contractor filed suit three years after the final decision was issued, challenging the government’s claim to the trust account funds.


Continue Reading Show Me the Money? When a Sum Approximate Counts as a Sum Certain

The American Rescue Plan Act of 2021 (the Act), signed into law by President Biden on March 11, 2021, extends Section 3610 of the CARES Act (previously discussed here, here, and here) through September 30, 2021. The extension allows federal agencies to reimburse contractors for six additional months of paid-leave costs if

In Globe Trailer Manufacturing, Inc., ASBCA No. 62594 (Jan. 28, 2021), the Armed Services Board of Contract Appeals (the Board) addressed whether a contractor’s certified supplement to a termination settlement proposal (TSP) constitutes a claim under the Contract Disputes Act. After termination, the contractor submitted a TSP that included costs of constructive changes. During

In BGT Holdings, Inv. v. United States, No. 1:18-cv-00178-PEC (Fed. Cir. Dec. 23, 2020), the Federal Circuit held that FAR 52.245-1 requires the Government to consider an equitable adjustment when it fails to provide Government-furnished equipment (GFE) required by the contract.  The contract in question required the Government to furnish equipment for the construction

On Sunday, President Trump signed a combined COVID-Relief and Omnibus Spending Bill, The Consolidated Appropriations Act of 2021, which funds the Federal Government for FY 2021 and includes a variety of COVID-19-related relief measures.  Among those measures, Section 1002 of the Act extends the reimbursement period for Section 3610 of the CARES Act, which

On December 9, 2020, the Department of Defense Office of Inspector General (DoD OIG) released its Audit of Department of Defense Implementation of Section 3610 of the Coronavirus Aid, Relief, and Economic Security Act.  The audit assesses the DoD’s issuance of relief under Section 3610, which authorizes certain agencies to reimburse contractors for any

In JKB Solutions and Servs., LLC, the Court of Federal Claims denied the contractor’s breach claim and held that the Government constructively terminated the contract for convenience. At issue was an Army contract to provide instructors for the Army’s Operation Contract Support program. The contract required JKB to perform 14 classes per task order,

The Armed Services Board of Contract Appeals published its FY2020 Report of Transactions and Proceedings, which provides statistics regarding the adjudication of appeals between contractors and the Army, Navy, Air Force, Corps of Engineers, CIA, NASA, DLA, DCMA, and other Defense agencies, Non-Appropriated Fund Instrumentalities, and the Washington Metropolitan Area Transit Authority. According to

On September 30, the Office of the Undersecretary of Defense for Acquisition and Sustainment issued a memorandum titled “Delegation of Defective Pricing Authority to the Defense Contract Management Agency,” describing DCMA’s new, enhanced role in TINA audits and subsequent disputes. The memo states that DCMA has created a “Defective Pricing Pilot Team,” which