Photo of Michelle Coleman

Michelle D. Coleman is a counsel in the Government Contracts Group in Crowell & Moring’s Washington, D.C. office. Michelle advises clients from diverse industries in connection with contract disputes and other government contract matters, including Contract Disputes Act (CDA) claims and requests for equitable adjustments, fiscal law questions, prime-sub disputes, and bid protests.

Congress has not passed crucial funding bills for the start of the fiscal year 2024.  If Congress does not act by September 30, the government may be forced to shut down for lack of funding.  While Congress may yet act, agencies across the government are preparing for a shutdown, and contractors should do so as well. 

The issues that contractors would face under a government shutdown may vary with the circumstances of individual contracts, but there are a number of common considerations.  Continue Reading Common Questions—and Answers—About A Potential Government Shutdown

On August 25, 2023, in ECC CENTCOM Constructors, LLC v. United States, COFC No. 21-1169, the U.S. Court of Federal Claims (“the Court” or “COFC”) barred ECC CENTCOM Constructors, LLC (“ECC”) from asserting claims that should have been asserted before the Armed Services Board of Contract Appeals (“ASBCA”) citing the doctrine of claim preclusion. 

At the ASBCA, ECC had appealed a termination for default and sought time extensions and damages due to excusable delay.  The Board dismissed ECC’s appeal, finding that the Contracting Officer (“CO”) acted reasonably in terminating the contract and finding that ECC failed to present its excusable delay claims to the CO as required under M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010).  ECC requested a stay to allow it time to present its delay claims to the CO, but the Board denied the request stating that it was untimely and futile because ECC’s own expert testified that less than half of the delays were excusable, which meant that the CO’s termination decision would still be justified.  ECC appealed the ASBCA’s decision to the U.S. Court of Appeals for the Federal Circuit, where the Board’s decision was affirmed.Continue Reading Strike When the Iron is Hot: Court of Federal Claims Found a Contractor’s Defense to a Termination Was Precluded by its Failure to Previously Assert Those Claims in Litigation Before the ASBCA

In StructSure Projects, Inc., ASBCA No. 62927, the Armed Services Board of Contract Appeals (Board) granted an appeal seeking recovery for increased costs resulting from the COVID-19 pandemic.  The underlying task order involved design and alteration services for existing medical facilities at Travis Air Force Base, and included a specific Contract Line Item Number (CLIN) for the provision of temporary phasing facilities that the Government could use while the construction work was ongoing.  When the pandemic began in March 2020, StructSure and its subcontractors had to stop their on-site construction work for 44 days because the Government had limited base access for contractors deemed to be not mission-essential.  StructSure later sought schedule and monetary relief, but the Government only granted schedule extensions under the Default clause.Continue Reading COVID Costs Claim Succeeds: Contractor Entitled to Recover for Performance of Contract Despite Base Closure

In ECC Int’l Constructors Inc. v. Army, No. 2021-2323 (Fed. Cir. Aug. 22, 2023), the Court of Appeals for the Federal Circuit overturned longstanding precedent by holding that the requirement to state a “sum certain” in a claim submitted under the Contract Disputes Act (CDA) is not a jurisdictional requirement.  The Court based its decision on recent Supreme Court guidance to “treat a procedural requirement as jurisdictional only if Congress ‘clearly states’ that it is.”  The Court parsed the CDA and found that Congress never used the words “sum certain,” evidencing that Congress did not intend the requirement to be jurisdictional.  This is important because jurisdictional requirements can be raised at any time—even years after the claim was filed and a full hearing on the merits was held—and result in dismissal of the case.  The Court explained that the “sum certain” is “nonetheless a mandatory rule that claimants must follow.” Continue Reading Sum-Thing Is Missing from the Contract Disputes Act: Federal Circuit Holds that “Sum Certain” Requirement is Non-Jurisdictional

On June 29, 2023, the Government Accountability Office (GAO) released its second report[1] on Department of Defense (DoD) artificial intelligence (AI) acquisition efforts.  This latest report examines the DoD’s lack of formal AI acquisition guidance and identifies key principles from the private sector that can be applied to the DoD’s AI acquisition efforts. 

Although

On May 15, 2023, the Armed Services Board of Contract Appeals (“ASBCA” or “the Board”) in J&J Maintenance, Inc., d/b/a J&J Worldwide Services, ASBCA No. 63013 issued an instructive analysis of its jurisdiction to hear monetary and nonmonetary claims.  Partially granting a government motion to dismiss, the ASBCA explained that, if a contractor does not seek monetary relief in its claim to the contracting officer (“CO”), then the contractor cannot seek monetary relief on appeal to the Board.  Addressing the contractor’s claim for contract interpretation, however, the Board denied the government’s motion to dismiss and held that, where a contractor can reasonably articulate “significant consequences” of its claim other than the recovery of money, the fact that the claim may also have a financial impact on the parties does not strip the Board of jurisdiction.  Continue Reading Money Talks, But So Do Other Impacts: ASBCA Underscores that a Claim with Possible Financial Impacts Is Not Fundamentally a Monetary Claim Unless It Has No Other Significant Consequences

On April 6, 2023, the Civilian Board of Contract Appeals (CBCA), in BES Design/Build, LLC, CBCA 7585, dismissed a contractor’s appeal for lack of jurisdiction, finding the appeal untimely, and underscoring that a contractor cannot reset the 90-day appeal window by resubmitting its original claim.

On February 24, 2021, BES Design/Build, LLC (BES) submitted

On April 18, 2023, the Department of Defense (“DoD”) issued guidance to DoD contracting officers directing the cessation of certain emergency contracting measures utilized during the COVID-19 pandemic.  Following the termination of the COVID-19 national emergency declaration through President Biden’s April 10, 2023 signing of H.J. Res. 7, DoD released a memorandum titled “

On December 30, 2022, New York Governor signed into law Labor Law Section 240-i, establishing a registration system for contractors and subcontractors engaged in public work and covered private projects in New York. This law will require contractors to register with the New York State Department of Labor (the “Department of Labor”) every two years, by submitting various disclosures about their businesses, in order to ensure that contractors do not have previous labor law violations, and will abide by New York labor laws and regulations, including prevailing wage requirements. The Department of Labor will establish and maintain a public on-line system where registrations and disclosures are available. Continue Reading New Registration Requirement for Contractors and Subcontractors Performing Public Works and Covered Private Projects in New York

On November 1, 2022, the Armed Services Board of Contract Appeals (ASBCA) published its FY 2022 Report of Transactions and Proceedings, which provides statistics regarding the adjudication of appeals between contractors and the Army, Navy, Air Force, Corps of Engineers, Central Intelligence Agency, National Aeronautics and Space Administration, Defense Logistics Agency, Defense Contract Management Agency