The following is an installment in Crowell & Moring’s Bid Protest Sustain of the Month Series. In this series, Crowell’s Government Contracts Practice keeps you up to date with a summary of one of the most notable bid protest sustain decisions each month. Below, Crowell Consultant (and former GAO Bid Protest Hearing Officer) Cherie Owen discusses GAO’s decision in Ares Enterprise, LLC, B-424548 et al., Sept. 3, 2026, which addressed a situation where an agency attempted to issue a task order that exceeded the scope of both the underlying blanket purchase agreement and the awardee’s Federal Supply Schedule contract.
Ares had been performing information technology (IT) support services at Los Angeles Air Force Base (LAAFB) as a subcontractor. Following a 2023 decision to transition all local IT contracts to the Enterprise Information Technology as a Service (EITaaS) Wave 1 Blanket Purchase Agreement (BPA), the Space Force sought to move the LAAFB work onto that vehicle. To do so, it issued a task order to Vision Information Technology Consultants under its EITaas BPA. Ares protested, arguing that the order exceeded the scope of both the BPA and Vision’s underlying Federal Supply Schedule (FSS) contract. GAO agreed on both counts.
When an agency issues an order that materially exceeds the scope of the underlying BPA, it effectively awards work on a sole-source basis to a vendor that was never evaluated or selected to perform that type of work, while excluding other vendors that might have competed for the requirement had it been properly solicited. In evaluating claims that an order is beyond the scope of its underlying contract, GAO applies a “material difference” test, asking whether the order is “of a nature which potential offerors [that would have competed for the BPA] reasonably would have anticipated.”
Here, GAO found that the EITaaS BPA was designed for a specific, defined slice of IT services. The BPA performance work statement described “Wave 1” services organized around three core areas: enterprise services (principally a help desk and IT service management platform), end user device management (covering laptops, mobile devices, printers, and voice devices), and device protection (security at the device level). In essence, the BPA was focused on ensuring individual employees have working computers, phones, and printers, that those devices are managed through a centralized service desk and that the devices are protected from malware and data loss. It was not built to cover the operation and maintenance of an agency’s entire network infrastructure.
The Space Force attempted to use this BPA to issue a task order that involved a considerably different scope. One task required Vision to operate and maintain an extensive list of networks, systems, and infrastructure, including Wi-Fi networks, external web servers, wide area networks, storage area networks, virtual desktops, backup power systems, and database, file, and application servers. Ares argued (and GAO agreed) that the BPA’s end user device scope simply did not cover the services described in the task order. An order requiring full network and infrastructure operations was not of a nature that potential offerors reasonably would have anticipated when the BPA was established. Firms that might have competed for end user device support had no reason to anticipate they would be called upon to operate and maintain an entire base’s network infrastructure.
GAO applied similar logic to cybersecurity work required under the task order, which required Vision to fill significant governance roles, including Information Systems Security Manager and Information Systems Security Officer, with individuals who would have day-to-day responsibility for cybersecurity compliance and system administration of a sensitive compartmented information network. GAO found that these broader cybersecurity services bore no resemblance to the BPA’s device-level security work scope, and the BPA itself confirmed that network-wide cybersecurity was reserved for future waves. GAO also found other work outside the BPA’s scope, including: an IT planning and technical solutions task; a knowledge management task (which required Vision to serve as a records manager, handle Freedom of Information Act requests, and process personally identifiable information breaches); and application development requirements.
While the agency attempted to rely on a general “catch-all” provision in the BPA’s engineering services task area, GAO declined to read such broad language as a general exception to the scope of the BPA. Citing its prior decision in DynCorp International LLC, B-402349, Mar. 15, 2010, GAO reaffirmed the principle that general statements in a contract do not serve to expand the contract’s scope beyond that which was anticipated during the competition. In short, broadly worded contract provisions cannot be used to expand scope beyond what was contemplated when the BPA was competed.
Ares’ second protest ground was also successful – Ares argued that the services envisioned by the task order were not within the scope of Vision’s FSS contract. In this regard, when an agency places an order under the FSS program, all items ordered must be on the vendor’s schedule contract. FSS delivery orders that fall outside the scope of the underlying FSS contract must be competed using full and open competition. Ares argued that the procurement here failed to comply with that requirement and GAO agreed.
GAO found that the agency lacked a factual basis for concluding that the task order fell within the scope of Vision’s FSS contract. Rather than mapping the order’s required labor categories to those actually on Vision’s schedule, the agency took the position that an order issued to a CTA (contractor teaming arrangement) member need not fall within the scope of that firm’s own FSS contract, so long as the required labor categories appear on another CTA member’s schedule. GAO squarely rejected that theory. Under GSA’s CTA framework, each team member is a prime contractor in privity of contract with the government under its own FSS contract. A CTA allows an agency to place orders with multiple team members for a single requirement, but it does not override the fundamental rule that each FSS contractor must operate within the scope of its own contract. Because the agency never analyzed whether the task order was within the scope of Vision’s FSS contract, GAO sustained the protest on this independent basis as well.
GAO’s Ares decision offers several practical takeaways for contractors. First, firms should not assume that the issuance of an order under a single-award BPA forecloses protest standing. GAO confirmed that a firm need not hold an FSS contract or be a BPA holder to challenge an order as exceeding the scope of the BPA or the recipient’s FSS contract because, if the protest is sustained, the resulting remedy may open the door for the protester to compete. Second, contractors unable to compete for work because it is being ordered under a contract vehicle to which they are not a party should scrutinize whether the contract vehicle’s scope actually encompasses the work being ordered under it. Finally, where an order is placed with a single CTA member, contractors should examine whether the order falls within the scope of that specific member’s FSS contract, not merely within the scope of the CTA as a whole, because a CTA does not allow one member to perform work under another member’s labor categories.