Photo of Nicole Owren-WiestPhoto of Erin RankinPhoto of Catherine Shames

In Strategic Technology Institute, Inc. v. Sec’y of Def., 91 F.4th 1140 (Fed. Cir. 2024), the Federal Circuit affirmed a decision by the Armed Services Board of Contract Appeals (ASBCA), which held that the government’s 2018 claim was not time-barred by the Contract Dispute Act’s (CDA) six-year statute of limitations.  The ASBCA found that the government’s claim did not begin to accrue until 2014, the date the government received the contractor’s indirect cost rate proposals for fiscal year (FY) 2008 and FY 2009. Continue Reading Start the Clock: Government’s Indirect Cost Rate Claim Accrued upon Submission of Indirect Cost Rate Proposal

Photo of Michelle ColemanPhoto of Erin RankinPhoto of Amanda McDowell

On remand from the U.S. Court of Appeals for the Federal Circuit, in ECC International Constructors, LLC, ASBCA Nos. 59586, 59643, the Armed Services Board of Contract Appeals concluded that, by waiting until after a hearing on the merits and six years after the appeal was filed, the government forfeited its right to challenge the contractor’s satisfaction of the FAR’s sum-certain requirement for Contract Disputes Act claims.Continue Reading Wait Too Long and You Might Miss Sum-Thing: ASBCA Again Underscores that Failure to Timely Raise Sum-Certain Defense Can Result in Forfeiture Under New Federal Circuit Precedent

Photo of Steve McBradyPhoto of Nicole Owren-WiestPhoto of Michelle ColemanPhoto of Charles BaekPhoto of Catherine ShamesPhoto of Zariah Altman

In Aviation Training Consulting, LLC, ASBCA No. 63634 (Jan. 11, 2024), the Armed Services Board of Contract Appeals (ASBCA) confirmed that a contractor’s properly asserted claim for relief under Section 3610 of the Coronavirus Aid, Relief, and Economic Security (CARES) Act is a claim under the Contract Disputes Act (CDA) and denied the Air Force’s motion to dismiss for lack of jurisdiction.Continue Reading Who CARES? The ASBCA Might.

Photo of Steve McBradyPhoto of Skye MathiesonPhoto of Michelle ColemanPhoto of Eric HerendeenPhoto of John NakonecznyPhoto of Tyler Piper

On November 1, 2023, the Armed Services Board of Contract Appeals (ASBCA) published its FY 2023 Report of Transactions and Proceedings, which provides statistics regarding the adjudication of appeals between contractors and the Army, Navy, Air Force, Corps of Engineers, Central Intelligence Agency, National Aeronautics and Space Administration, Defense Logistics Agency, Defense Contract Management

Photo of Michelle ColemanPhoto of Amanda McDowellPhoto of Zariah Altman

On August 25, 2023, in ECC CENTCOM Constructors, LLC v. United States, COFC No. 21-1169, the U.S. Court of Federal Claims (“the Court” or “COFC”) barred ECC CENTCOM Constructors, LLC (“ECC”) from asserting claims that should have been asserted before the Armed Services Board of Contract Appeals (“ASBCA”) citing the doctrine of claim preclusion. 

At the ASBCA, ECC had appealed a termination for default and sought time extensions and damages due to excusable delay.  The Board dismissed ECC’s appeal, finding that the Contracting Officer (“CO”) acted reasonably in terminating the contract and finding that ECC failed to present its excusable delay claims to the CO as required under M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010).  ECC requested a stay to allow it time to present its delay claims to the CO, but the Board denied the request stating that it was untimely and futile because ECC’s own expert testified that less than half of the delays were excusable, which meant that the CO’s termination decision would still be justified.  ECC appealed the ASBCA’s decision to the U.S. Court of Appeals for the Federal Circuit, where the Board’s decision was affirmed.Continue Reading Strike When the Iron is Hot: Court of Federal Claims Found a Contractor’s Defense to a Termination Was Precluded by its Failure to Previously Assert Those Claims in Litigation Before the ASBCA

Photo of Michelle ColemanPhoto of John NakonecznyPhoto of Tyler Piper

In StructSure Projects, Inc., ASBCA No. 62927, the Armed Services Board of Contract Appeals (Board) granted an appeal seeking recovery for increased costs resulting from the COVID-19 pandemic.  The underlying task order involved design and alteration services for existing medical facilities at Travis Air Force Base, and included a specific Contract Line Item Number (CLIN) for the provision of temporary phasing facilities that the Government could use while the construction work was ongoing.  When the pandemic began in March 2020, StructSure and its subcontractors had to stop their on-site construction work for 44 days because the Government had limited base access for contractors deemed to be not mission-essential.  StructSure later sought schedule and monetary relief, but the Government only granted schedule extensions under the Default clause.Continue Reading COVID Costs Claim Succeeds: Contractor Entitled to Recover for Performance of Contract Despite Base Closure

Photo of Steve McBradyPhoto of Skye MathiesonPhoto of Michelle ColemanPhoto of Eric HerendeenPhoto of John NakonecznyPhoto of Amanda McDowellPhoto of J. Chris Haile

On May 15, 2023, the Armed Services Board of Contract Appeals (“ASBCA” or “the Board”) in J&J Maintenance, Inc., d/b/a J&J Worldwide Services, ASBCA No. 63013 issued an instructive analysis of its jurisdiction to hear monetary and nonmonetary claims.  Partially granting a government motion to dismiss, the ASBCA explained that, if a contractor does not seek monetary relief in its claim to the contracting officer (“CO”), then the contractor cannot seek monetary relief on appeal to the Board.  Addressing the contractor’s claim for contract interpretation, however, the Board denied the government’s motion to dismiss and held that, where a contractor can reasonably articulate “significant consequences” of its claim other than the recovery of money, the fact that the claim may also have a financial impact on the parties does not strip the Board of jurisdiction.  Continue Reading Money Talks, But So Do Other Impacts: ASBCA Underscores that a Claim with Possible Financial Impacts Is Not Fundamentally a Monetary Claim Unless It Has No Other Significant Consequences

Photo of Nicole Owren-WiestPhoto of Erin RankinPhoto of Catherine Shames

In Voxtel, Inc., ASBCA No. 60129 (March 9, 2023), the Armed Services Board of Contract Appeals (ASBCA) issued a decision that presents a primer on the resolution of indirect cost rate disputes.  The ASBCA granted the contractor’s appeal in part, finding that its claimed executive compensation and independent research and development (IR&D) costs were allowable, but that certain rental costs related to the “fit-up” of a leased facility were unallowable.

The Defense Contract Audit Agency (DCAA) performed “adequacy” and “nomenclature” reviews of Voxtel’s indirect cost rate proposals (or incurred cost proposals, “ICPs”) for fiscal years 2007 to 2009, but did not conduct audits.  The Contracting Officer (CO) then issued a final decision unilaterally setting indirect rates and finding that the ICPs included unallowable executive compensation, IR&D, and rental costs.  The contractor appealed. Continue Reading If At First You Don’t Succeed: Contractor Successfully Challenges Disallowed IR&D and Compensation Costs

Photo of Nicole Owren-WiestPhoto of Erin RankinPhoto of Alexandra Barbee-GarrettPhoto of Catherine ShamesPhoto of Zariah Altman

In General Atomics Aeronautical Systems, Inc., ASBCA Nos. 61633, 61731 (Feb. 8, 2023), released March 14, 2023, the Armed Services Board of Contract Appeals (ASBCA) considered, but declined to answer, the existential question of whether intracompany lease payments are “costs.”  The ASBCA denied the Government’s motion for summary judgment, finding that material facts about the

Photo of Peter J. EyrePhoto of M.Yuan Zhou

This week’s episode covers annual reports from GAO and the ASBCA, a proposed rule regarding disclosure of greenhouse gas emissions and climate-related financial risk, and new requirement to refer any suspected instances of human trafficking to suspension and debarment officials, and is hosted by Peter Eyre and Yuan Zhou. Crowell & Moring’s “Fastest 5 Minutes”